The engine compartments are finished to take up the 30hp inboard engines plus 12V 800A alternators and 380V 8kW generator.
Read More
Generic
Jan 09, 2012 | Post by: wavescalpel (mr) 1 Comments
WaveScalpel manufacturing diary 2012-01-09
The alloy part of hulls and bridge is finished. Woodworks are started. The story continues in May 2012
Read More
Read More
Sep 03, 2009 | Post by: wavescalpel (mr) No Comments
Logistics: Container arrival
After several visits at the customs in Heraklion/Crete, finally the container arrived safely on the building site.
Read More
Read More
Aug 05, 2009 | Post by: wavescalpel (mr) No Comments
the empty building site
The antecessor has left his birth place and now my boat can be started. Unfortunately the shipped container has a “short” delay…….
Read More
Read More
Jul 29, 2009 | Post by: wavescalpel (mr) No Comments
antecessor
Jul 22, 2009 | Post by: wavescalpel (mr) No Comments
going to Crete by camper van
Jul 20, 2009 | Post by: wavescalpel (mr) No Comments
Logistics: Container shipping
The container is filled with 20 tons of alloy, stainless steel, tools and equipment for building the 18m x 10m bluewater cruising catamaran.
Read More
Read More
May 29, 2009 | Post by: wavescalpel (mr) No Comments
Logistics: Loading 15 tons of metal
finally two strong men have to close the container door. This means there can’t be a lot of movement in the container. But it was raising my heart beat rate. End of May the material is arranged so that the engines and other equipment plus tools can be stowed.
Read More
Read More
Apr 07, 2009 | Post by: wavescalpel (mr) No Comments